VolkerRail was awarded works under the Hochtief/Network Rail alliance to design build and commission the Hitchin Grade Separation; a new railway line to carry trains from the East Coast Main Line (ECML), in the down direction, over a new 29 span 800m viaduct and 1.2km chalk filled embankment, to join the down Cambridge line.
This was a two year; £6.2 million project and VolkerRail delivered all the rail system elements including design, p-way, OLE, signalling and E&P works. The roject involved the construction of a new single track electrified railway providing a grade separated link, partly on a viaduct structure and partly on embankment, which now allows Cambridge bound trains from London to pass over the top of the ECML; thus increasing reliability and assisting in improving capacity.
The new junction is positioned at Hitchin north junction approximately 1.1km North of Hitchin station, to link the down slow and down fast lines of the ECML with the Down Cambridge line.
The programme was split into four phases:
The main contract for VolkerRail commenced in August 2011 and was commissioned June 2013, five months ahead of schedule.
As specialist partner to the Network Rail/Hochtief alliance, VolkerRail has successfully completed the rail systems element of...
VolkerRail has been awarded the major share of signalling frameworks within Network Rail’s signalling strategy for...