VolkerRail is continuing to replace track sections that have suffered wear and tear on the street running rails of the Sheffield Supertram network.
This project is a continuation of the first phase of the Supertram Rail Replacement scheme, which VolkerRail completed between 2013 and 2015; with successful results.
The new project has been broken down into three stages, with work beginning on 26 May 2018.
Phase one saw VolkerRail replace more than 12km of track.
Over the course of this phase, VolkerRail will replace approximately 9.5km of track with the aim of improving passenger comfort and reducing noise levels.
The first stage of works has been broken down into five areas, which will be completed from May through to September 2018:
Area 1 |
Hillsborough and Middlewood |
Area 2 |
Birley Lane – Halfway |
Area 3 |
Gleadless Townend – Herdings Park |
Area 4 |
Gleadless Townend – Halfway/Herdings Park |
Area 5 |
Donetsk Way - Halfway |
All three stages are due to finish in the summer of 2020.
For information on bus and traffic diversions via its website travelsouthyorkshire.com/RailReplacement
VolkerRail has been awarded a new Embedded Framework contract, by Transport for London (TfL), to undertake track renewals...
VolkerRail has been appointed to complete essential track work in Nottingham city centre.