The Hope Valley line improvements are nearing completion, with significant track and signalling work completed over the weekend, despite harsh weather conditions.

VolkerRailStory joint venture - Hope Valley Railway Upgrade - Grindleford - January 2024 (1).jpg

Between Stockport and New Mills, a new signalling system covering over 13 miles of track was commissioned into service. This new system will improve the line speed capability for trains, marking the completion of upgrades along this section of the line.

Towards Sheffield, 380m of track was installed in Grindleford, including 1,850 tonnes of ballast and 430 sleepers.

The first set of stairs was also lifted in for a new, accessible footbridge, at Dore & Totley station, to connect the structure to the existing platform.

Graeme Whitehead, senior sponsor for the Hope Valley Railway Upgrade, said: “This was an important weekend for the scheme as we installed new track, carried out signalling upgrades and further platform works at Dore & Totley.

“It brings us another step closer to improving the connectivity of Manchester and Sheffield, and realising the benefits for passengers travelling by train.”

Jim Goldsby, project director from VolkerRailStory JV, said: “It’s been a successful weekend on the project, where the team reacted well to challenges created by difficult weather conditions. We’re pleased with the progress of work so far and are looking forward to completing the scheme over the coming months.”

The work, delivered for Network Rail by a joint venture of VolkerRail and Story Contracting, was carried out during the first of four successive weekend railway line closures being undertaken throughout January and February.

The next three weekends will see the final upgrades continue in Grindleford and Dore & Totley, before a nine day railway line closure at the end of March, which will enable the project’s completion.

News

More news

Final track installed for Bamford passing loop to remove historic bottlenecks along...

The final pieces of track have been installed to help relieve a long-standing bottleneck on the Hope Valley railway line,...

Hope Valley Railway Upgrade nears completion

The VolkerRailStory joint venture will be undertaking works to complete the final phase of the Hope Valley Railway Upgrade .

Milestone reached on construction of Bamford loop for Hope Valley Railway Upgrade

Progress is continuing on the Hope Valley Railway Upgrade , as the VolkerRailStory joint venture continues to undertake...

+